Project Update

26 Jul 2018 07:00

RNS Number : 7964V
Ncondezi Energy Limited
26 July 2018
 

 

News Release 

 

 

Project Update

 

26 July 2018: Following the announcement on 29 June 2018, Ncondezi Energy Limited ("Ncondezi" or the "Company") (AIM: NCCL) provides the following update on its process to conclude a binding Joint Development Agreement ("JDA") for the Company's integrated 300MW power and coal mine project in Tete Mozambique (the "Project").

 

Key Highlights:

 

· Updated tariff proposal (the "Proposal") formally submitted to Mozambican state power utility Electricity de Mozambique ("EDM") and the Ministry of Mineral Resources and Energy ("MIREME").

 

· EDM has requested a detailed workshop session (the "Workshop") with the Company and its potential strategic partners to work through the updated tariff proposal and agree critical next steps following receipt of the Proposal and initial meetings held in July 2018.

 

· Workshop timing is planned for early August 2018.

 

· The submission forms part of the process to receive formal support from EDM and MIREME to progress the Project, and is a key milestone in finalising the JDA.

 

· Ncondezi now targeting JDA completion within 3 months of receipt of necessary support from EDM and MIREME with more clarity on timing expected post the Workshop in August 2018.

 

· Updated timetable for key milestones including the power tariff sign off, Power Purchase Agreement ("PPA") negotiations, Financial Close ("FC") and the date of first power on the grid expected to be agreed during the Workshop.

 

· Further updates will be provided after the Workshop has been concluded.

 

· EDM has released 10 year strategy paper which includes provision for 300MW of coal fired power from Tete Mozambique in 2023, which is within the Project's current delivery timeline.

 

Ncondezi's Non-Executive Chairman, Michael Haworth, commented: "Whilst it is disappointing that the JDA will not be finalised by the end of July, the Company is encouraged by the response it has received to date from EDM following delivery of the Proposal, and believes that this is as a result of a competitive and attractive package that the Company and its potential strategic partners have put together. EDM has indicated the need for a 300MW coal fired project on the grid by 2023 in its 2018 10 year strategy paper to fill a critical power shortfall and energy mix need in the north of the country. The Company believes that the Project is well positioned to deliver on this as one of the most advanced power development projects in Mozambique together with world class potential strategic partners. The next critical step is to successfully complete the Workshop in August 2018, receive the necessary support from EDM and MIREME to finalise the JDA and agree the updated schedule for the key milestones leading up to FC and commissioning. Further updates on the timetable for delivery of the JDA and other key work streams are expected to be provided after the Workshop.

 

 

 

There is no certainty that the transactions contemplated by this announcement will occur.

 

Enquiries

For further information please visit www.ncondezienergy.com or contact:

 

Ncondezi Energy:

Hanno Pengilly

+27 (0) 71 362 3566

 

Liberum Capital Limited:NOMAD & Joint Broker

 

Neil Elliot / Richard Crawley

+44 (0) 20 3100 2000

Novum Securities Limited:

Joint Broker

Colin Rowbury

+44 (0) 20 7399 9427

 

Note:

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulation ("MAR"). Upon the publication of this announcement via Regulatory Information Service ("RIS"), this inside information is now considered to be in the public domain. If you have any queries on this, then please contact Hanno Pengilly, Chief Development Officer of the Company (responsible for arranging release of this announcement) on +27 (0) 71 362 3566.

 

 

Ncondezi owns 100% of the Ncondezi Project which is strategically located in the power generating hub of the country, the Tete Province in northern Mozambique. The Company is developing an integrated thermal coal mine and power plant in phases of 300MW up to 1,800MW. The first 300MW phase is targeting domestic consumption in Mozambique using reinforced existing transmission capacity to meet current demand.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDLLFVDDSIEFIT
Date   Source Headline
30th Sep 20147:00 amRNS2014 Interim Results
10th Sep 20147:00 amRNSNcondezi reaches Commercial Deal with EdM
14th Aug 20143:18 pmRNSResult of AGM
22nd Jul 20144:38 pmRNSNotice of AGM
10th Jul 20147:00 amRNSNcondezi Power Project Update
3rd Jul 20142:18 pmRNSHolding(s) in Company
27th Jun 20147:00 amRNSPosting of Annual Report and Accounts
20th May 20147:00 amRNSAudited Final Results for Year Ended 31 Dec 2013
8th Apr 20147:00 amRNSNcondezi Power Upate
4th Mar 20147:00 amRNSNcondezi Receives Power Plant EPC Binding Bids
21st Feb 20147:00 amRNSNcondezi Initiates Tender Process
17th Feb 20147:00 amRNSDirectorate Change
31st Jan 20147:00 amRNSShare Option Grants
7th Jan 20145:30 pmRNSHolding(s) in Company
7th Jan 20144:47 pmRNSHolding(s) in Company
7th Jan 201411:10 amRNSHolding(s) in Company
7th Jan 201410:27 amRNSHolding(s) in Company
2nd Jan 20149:28 amRNSHolding(s) in Company
27th Dec 201311:13 amRNSHolding(s) in Company
23rd Dec 20138:02 amRNSAdmission of Shares
23rd Dec 20137:00 amRNSPower Framework Agreement Effective
20th Dec 20137:00 amRNSOptimised Mine Feasibility Study
18th Dec 20137:00 amRNSRESULT OF OPEN OFFER AND PLACING
12th Dec 20137:00 amRNSPower Plant Ownership Structure Heads of Terms
2nd Dec 20137:00 amRNSOPEN OFFER AND PLACING OF NEW ORDINARY SHARES
18th Nov 20137:00 amRNSPower Plant Update
18th Nov 20137:00 amRNSCoal Resource Upgrade
7th Nov 20137:00 amRNSNcondezi Initiates EPC Binding Proposal Process
4th Nov 20137:00 amRNSESIA Approval for Ncondezi Power Plant
29th Oct 20137:00 amRNSNcondezi Energy Directorate Change(s)
14th Oct 20137:00 amRNSNcondezi Energy Signs Power Purchase Head of Terms
8th Oct 20137:00 amRNSNcondezi Mine Update and ESIA Approval
16th Sep 20137:00 amRNSNcondezi Energy Appoints Project Financial Adviser
28th Aug 20137:00 amRNSNcondezi Energy Granted Coal Mining Concession
9th Aug 20137:00 amRNSInterim Results for six months ended 30 June 2013
29th Jul 20137:00 amRNSName Change to Ncondezi Energy
26th Jul 20132:52 pmRNSResults of Annual General Meeting 2013
19th Jul 20132:16 pmRNSHolding(s) in Company
28th Jun 20137:00 amRNSAudited Final Results for Year Ended 31 Dec 2012
3rd Jun 20137:05 amRNSHolding(s) in Company
3rd Jun 20137:00 amRNSHolding(s) in Company
26th Apr 20137:00 amRNSCEO Appointment Confirmed & Grant of Share Awards
25th Apr 20137:00 amRNSNCCL Signs Power Framework Agreement w Mozambique
13th Mar 20137:00 amRNSNcondezi commences EPC selection process
25th Feb 20137:00 amRNSManagement And Name Change
5th Feb 20137:00 amRNSNcondezi Strengthens Board with Power Expertise
10th Jan 201310:21 amRNSHolding(s) in Company
4th Dec 20127:00 amRNSProject Update: Development of 300MW Power Project
16th Oct 20123:22 pmRNSHolding(s) in Company
17th Sep 201210:54 amRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.