Ncondezi reaches Commercial Deal with EdM

10 Sep 2014 07:00

RNS Number : 2481R
Ncondezi Energy Limited
10 September 2014
 



News Release

 

 

Ncondezi reaches Commercial Deal with EdM

 

Highlights

· Tariff range agreed for 25 year Power Purchase Agreement

· Tariff range supports Ncondezi Power Project economics

· Targeting substantially concluding PPA and PCA by end of 2014

 

10 September 2014: Ncondezi Energy Limited ("Ncondezi" or the "Company") (AIM: NCCL) is pleased to announce that it has reached a commercial deal with Electricidade de Mozambique ("EdM") on the sale of electricity from the Ncondezi Power Project (the "Project").

 

The agreed commercial deal includes the range for the starting electricity tariff to be paid by EdM, which will then be subject to adjustments during the 25 year operational life of the Project. The commercial deal is subject to a number of conditions precedent, to be satisfied by the end of 2014, including the introduction of a strategic investor acceptable to EdM, confirmation of the availability of political and commercial risk cover, bankable EPC contracts, bankable and acceptable O&M operator arrangements and agreeing a timetable for the substantial completion of all key project agreements involving EdM.

 

This announcement is a result of negotiations and progress over the last six months between Ncondezi, EdM and the Mozambique Department of Energy ("DoE") on critical matters to the Project's viability, including the structure and content of key project agreements (in particular the Power Purchase Agreement ("PPA") and the Power Concession Agreement ("PCA")), the PPA tariff (level, structure and indexation) and the terms of credit support to be provided for the Project.

 

The EdM Board of Directors has approved the commercial deal and conditions precedent and endorsed continued negotiations between the parties with a view to concluding the key project agreements by end of 2014. The PPA and PCA are both anticipated to be finalised in conjunction with the EPC contract and O&M operator arrangements, and once approved, are expected to be initialled by EdM and DoE and will be executed at Financial Close which is targeted for H1 2015.

 

Commenting on the announcement, CEO Paul Venter said, "This is a very significant milestone for Ncondezi and is the culmination of all our hard work over the last 2 years. We would like to thank EDM and the Department of Energy for their ongoing support and we look forward to continuing to work with them as we move to towards Financial Close targeted for H1 2015 following which construction is expected to begin in H2 2015."

 

 

Enquiries:

For further information please visit www.ncondezienergy.com or contact:

 

Ncondezi Energy:

Hanno Pengilly / Alex Buck

+44 (0) 20 7183 5402

Liberum Capital Limited:NOMAD & Broker

Simon Atkinson / Christopher Britton

+44 (0) 20 3100 2000

finnCap:

Joint Broker

Matthew Robinson / Elizabeth Johnson /

Joanna Weaving

+44 (0) 20 7220 0500

Bell Pottinger:

Daniel Thöle / Marianna Bowes

+44 (0) 20 3772 2555

 

Ncondezi Energy owns 100% of the Ncondezi Project which is strategically located in the power generating hub of the country, the Tete Province in northern Mozambique. The Company is developing an integrated thermal coal mine and power plant in phases of 300MW up to 1,800MW. The first 300MW phase is targeting domestic consumption in Mozambique using reinforced existing transmission capacity to meet current demand and commercial operations are targeted for H1 2018.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
AGRLLMRTMBBMBFI
Date   Source Headline
28th Feb 202312:30 pmRNSResult of EGM
13th Feb 20237:00 amRNSNotice of EGM – Change of Name – Solgenics Limited
9th Feb 20237:00 amRNSDirector/PDMR Shareholding
6th Feb 20237:00 amRNSConvertible Loan Fully Converted
18th Jan 20237:00 amRNSPDMR Dealing
17th Jan 20237:00 amRNSPDMR Dealing & Conversion Notice
16th Jan 20237:00 amRNSConvertible Loan Conversions
13th Jan 20237:00 amRNSTransmission Route Approved
10th Jan 20234:35 pmRNSPrice Monitoring Extension
9th Jan 20237:00 amRNSSolar Land Agreement
30th Dec 202211:05 amRNSResult of AGM
22nd Dec 20227:00 amRNSAppointment of Solar Project Advisors
20th Dec 20221:08 pmRNSHolding(s) in Company
2nd Dec 20227:00 amRNSNotice of AGM
23rd Nov 202211:18 amEQSNcondezi Energy provides fresh numbers for Mozambique solar project
21st Nov 20227:30 amRNSPlacing
21st Nov 20227:00 amRNSSolar Valuation Update
31st Oct 20227:00 amRNSPositive Solar Feasibility Draft Delivered
25th Oct 20222:42 pmEQSNcondezi Energy pivoting to solar in Mozambique
21st Oct 20227:00 amRNSStrategic review of Coal Asset
30th Sep 20227:00 amRNSHalf-year Report
29th Sep 20227:00 amRNSSolar Feasibility Study Update
28th Sep 20222:06 pmRNSSecond Price Monitoring Extn
28th Sep 20222:00 pmRNSPrice Monitoring Extension
16th Sep 20227:00 amRNSConvertible Loan Finalised
1st Aug 202212:15 pmRNSSolar FS Update and Loan Restructuring
15th Jul 20227:00 amRNSSolar Project FS Launched with target NPV $60m
11th Jul 20229:46 amRNSSeritza Loan Restructuring Agreed "In Principle"
30th Jun 20227:00 amRNSSeritza Loan Extension
27th Jun 20227:00 amRNSAnnual Financial Report
1st Jun 20227:00 amRNSSeritza Loan Extension
12th May 20222:05 pmRNSSecond Price Monitoring Extn
12th May 20222:00 pmRNSPrice Monitoring Extension
12th May 202211:06 amRNSSecond Price Monitoring Extn
12th May 202211:00 amRNSPrice Monitoring Extension
12th May 20229:05 amRNSSecond Price Monitoring Extn
12th May 20229:00 amRNSPrice Monitoring Extension
11th May 20227:00 amRNSDirector/PDMR Shareholding
9th May 20227:00 amRNSPotential for Significant Solar & Battery Project
29th Apr 20227:00 amRNSSeritza Loan Extension
29th Mar 20227:00 amRNSWorking Capital Extended & Seritza Loan Update
25th Feb 20227:00 amRNSWorking Capital Facility Update
21st Feb 20222:06 pmRNSSecond Price Monitoring Extn
21st Feb 20222:01 pmRNSPrice Monitoring Extension
21st Feb 202211:06 amRNSSecond Price Monitoring Extn
21st Feb 202211:00 amRNSPrice Monitoring Extension
18th Feb 20229:05 amRNSSecond Price Monitoring Extn
18th Feb 20229:00 amRNSPrice Monitoring Extension
31st Jan 20227:00 amRNSTotal Voting Rights
19th Jan 20224:41 pmRNSSecond Price Monitoring Extn

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.