Update on Financing Plan

15 Apr 2014 14:00

RNS Number : 8868E
First Quantum Minerals Ld
15 April 2014
 



 

NEWS RELEASE

14-14

April 15, 2014

www.first-quantum.com

 

 

 

FIRST QUANTUM MINERALS PROVIDES AN UPDATE ON ITS FINANCING PLAN

 

First Quantum Minerals Ltd. ("First Quantum" or the "Company", TSX Symbol "FM", LSE Symbol "FQM") is pleased to announce that it has signed and drawn down on its $2.5 billion Five-Year Term Loan and Revolving Facility (the "$2.5 billion Facility").

 

The $2.5 billion Facility comprises a $1 billion Term Loan Facility available to draw until April 8, 2016 with a margin of 2.75% and a $1.5 billion Revolving Credit Facility available to draw until March 8, 2019 also with a margin of 2.75% per annum. All outstanding loans on these facilities must be repaid no later than April 8, 2019. The initial Mandated Lead Arrangers and Underwriters were Standard Chartered Bank and BNP Paribas. The $2.5 billion Facility is being syndicated, which is expected to close in May. The $2.5 billion Bridge Facility with Standard Chartered Bank arranged for the Inmet Mining Corporation ("Inmet") acquisition, which was completed in April 2013, has been cancelled.

 

The signing of the $2.5 billion Facility is a significant milestone in the Company's financial plan following the completion of the acquisition of Inmet. Other financing initiatives include the following:

 

· Exchange Offer - On February 27, 2014 the Company completed an exchange offer (the "Exchange Offer") whereby the 8.75% Senior Notes due 2020 and 7.50% Senior Notes due 2021 issued by Inmet prior to the acquisition (the "Inmet Notes") were exchanged for 6.75% Senior Notes due 2020 and 7.00% Senior Notes due 2021, issued by First Quantum (together, the "FQM New Notes").

· Consent Solicitation - On February 12, 2014 the Company completed a consent solicitation to make certain amendments to the $350 million indenture dated October 10, 2012 (the "Indenture") governing the Company's outstanding 7.25% Senior Notes due 2019 (the "FQM Notes"). The amendments, among other things, aligned the terms of the FQM Notes with the FQM New Notes.

· Kansanshi $1 billion Facility - On April 3, 2014 the Company cancelled its $1 billion Facility for Kansanshi Mining PLC, the owner of the Kansanshi copper and gold mine in Zambia. This $1 billion Facility was replaced by an unsecured $350 million Facility from Standard Chartered Bank, which became available for drawing on April 3, 2014.

· Kevitsa $250 million Facility - On February 11, 2014 the Company cancelled its $250 million Kevitsa Facility.

· ENRC $500 million Promissory Note - On March 20, 2014 the Company agreed to revise the terms of its $500 million Promissory Note from Eurasia Natural Resource Corporation ("ENRC"). The $500 million Promissory Note was issued to the Company as a result of the settlement of its dispute with ENRC relating to the Company's former assets in the Democratic Republic of Congo. ENRC delisted from the London Stock Exchange in Q4 2013 triggering the mandatory prepayment of the $500 million Promissory Note. The Company negotiated with ENRC a $70 million principal reduction of the $500 million Promissory Note as well as the payment of all outstanding interest at 3% then due. A new $430 million Promissory Note was issued by a subsidiary of ENRC on March 20, 2014 with a term to final maturity of December 31, 2015. The interest rate on the $430 million Promissory Note has been increased from 3% to 5% with all interest at 5% of approximately $40 million prepaid until the final maturity date. The $430 million Promissory Note is secured against the shares in a subsidiary holding ENRC's Mozambique coal assets and will be guaranteed by ENRC Congo B.V, a wholly owned subsidiary of ENRC.

· $100 million equipment financing facility - On April 2, 2014 the Company completed a $100 million equipment finance facility with Caterpillar Financial Services Corporation for Kalumbila Minerals Limited, which owns the Trident Project in Zambia. This equipment financing facility will be used to purchase mobile equipment for the Sentinel and Enterprise Mines and is guaranteed by the Company.

 

 

 

Philip Pascall, First Quantum's Chairman and Chief Executive, commented

 

"To have achieved this financing restructuring within 12 months of the acquisition of Inmet is a significant accomplishment. From the beginning, we recognized just combining the financing facilities of First Quantum and Inmet was not optimal for the larger, more diversified consolidated company. The new financing structure is cost efficient and flexible providing the Company with the financial resources to complete our major development programs."

 

The Company will continue to explore further alternatives for improving the flexibility of its financing plan.

 

On Behalf of the Board of Directors 12g3-2b-82-4461

of First Quantum Minerals Ltd. Listed in Standard and Poor's

G. Clive Newall

President

For further information visit our web site at www.first-quantum.com

 

North American contact: Sharon Loung, Director, Investor RelationsTel: (647) 346-3934 Fax: (604) 688-3818 Toll Free: 1 (888) 688-6577 E-Mail: sharon.loung@fqml.com United Kingdom contact: Clive Newall, PresidentTel: +44 140 327 3484 Fax: +44 140 327 3494 E-Mail: clive.newall@fqml.com

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCLLFEFSRIELIS
Date   Source Headline
10th Dec 20104:05 pmRNSBlocklisting Interim Review
3rd Dec 201012:42 pmRNSTotal Voting Rights
26th Nov 20104:40 pmRNSSecond Price Monitoring Extn
26th Nov 20104:35 pmRNSPrice Monitoring Extension
22nd Nov 20102:28 pmRNSDirector/PDMR Shareholding
10th Nov 20107:00 amRNS3rd Quarter Results
2nd Nov 20109:53 amRNSTotal Voting Rights
27th Oct 20104:15 pmRNSFirst Quantum Granted Interim Measures Orders
20th Oct 20107:00 amRNSQ3 2010 PRODUCTION
18th Oct 20107:05 amRNSFIRST QUANTUM MINERALS TO ACQUIRE ANTARES MINERALS
13th Oct 20102:15 pmRNSProgress Report on Drilling and Evaluation Program
5th Oct 201011:55 amRNSTotal Voting Rights
1st Oct 20107:00 amRNSLaunch of International Arbitration
29th Sep 201011:48 amRNSDirector/PDMR Shareholding
23rd Sep 20104:16 pmRNSDirector/PDMR Shareholding
15th Sep 20107:00 amRNSCommencement of Legal Proceedings
9th Sep 20107:00 amRNSStatement Re: Possible Legal Action
7th Sep 20105:00 pmRNSIssuance of Shares
2nd Sep 20105:48 pmRNSTotal Voting Rights
31st Aug 20107:00 amRNSSuspension of operations at Frontier mine
27th Aug 201012:58 pmRNSAdjustment of Conversion Price
24th Aug 20104:40 pmRNSSecond Price Monitoring Extn
24th Aug 20104:35 pmRNSPrice Monitoring Extension
23rd Aug 20107:00 amRNSUpdate on Legal Proceedings in DRC
17th Aug 20103:00 pmRNSNew Director Appointment
11th Aug 20107:00 amRNS2nd Quarter Results
11th Aug 20107:00 amRNSDividend Declaration
5th Aug 20107:00 amRNSTotal Voting Rights
4th Aug 20102:15 pmRNSUpdate on KMT Legal Proceedings
27th Jul 20104:41 pmRNSSecond Price Monitoring Extn
27th Jul 20104:35 pmRNSPrice Monitoring Extension
26th Jul 20102:00 pmRNSPROGRESS REPORT
21st Jul 20102:00 pmRNSNotice of Results
21st Jul 20107:00 amRNSDirector/PDMR Shareholding
20th Jul 20102:16 pmRNSQ2 Production
15th Jul 20107:00 amRNSDirector/PDMR Shareholding
7th Jul 20105:15 pmRNSPROVIDES ASSISTANCE TO RDC
5th Jul 20107:00 amRNSTotal Voting Rights
29th Jun 20104:35 pmRNSPrice Monitoring Extension
2nd Jun 20108:59 amRNSTotal Voting Rights
24th May 20107:00 amRNSUPDATE ON SODIMICO PROCEEDINGS
19th May 20104:40 pmRNSSecond Price Monitoring Extn
19th May 20104:35 pmRNSPrice Monitoring Extension
11th May 20107:00 amRNS1st Quarter Results
10th May 201010:46 amRNSAnnual Information Update
4th May 20109:36 amRNSTotal Voting Rights
28th Apr 20107:00 amRNSFirst Quarter Results To Be Published On May 10
21st Apr 20104:40 pmRNSSecond Price Monitoring Extn
21st Apr 20104:35 pmRNSPrice Monitoring Extension
19th Apr 20107:00 amRNSDirector/PDMR Shareholding

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.