The next focusIR Investor Webinar takes places on Weds 10th July at 6 PM with guest speakers from Pyx Resources (PYX), Helium One (HE1), Fulcrum Metals (FMET) and Metals One (MET1). Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksFDI.L Regulatory News (FDI)

  • There is currently no data for FDI

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Quarterly Update on Construction & Commissioning

26 Jan 2017 07:00

RNS Number : 1386V
Firestone Diamonds PLC
26 January 2017
 

26 January 2017

 

Firestone Diamonds plc

("Firestone", the "Group" or the "Company") (AIM: FDI)

 

Quarterly Update on Construction and Commissioning Activities

 

Firestone Diamonds plc, the AIM-quoted diamond company, is pleased to provide its quarterly update on construction and commissioning activities at its Liqhobong Diamond Mine ("Liqhobong" or the "Project") for the quarter ended December 2016. Liqhobong is owned 75% by Firestone and 25% by the Government of Lesotho.

 

Highlights for the quarter ended 31 December 2016

· Project construction 100% complete and ramping up to nameplate capacity

· First diamond recoveries commenced in late October 2016

· Recovery of over 20 special stones larger than 10.8 carats, with the largest being a 37 carat white diamond, as well as several fancy yellow diamonds

· Processing of lower grade stockpiles and diluted ore in the quarter produced 58,000 carats at a grade of 14.4 carats per hundred tonnes

· 402,000 tonnes treated by the processing plant and nameplate capacity achieved on multiple occasions

· Strong operating cost management of US$12 per tonne treated at bottom end of guidance

· Zero lost time injury record maintained, with approximately 3.6 million man hours worked

· Strong financial position with cash and available facilities of US$18 million, alongside a further US$15 million standby facility available

· First sale of Liqhobong diamonds will be held in Antwerp, Belgium from 6-10 February 2017

 

Stuart Brown, Chief Executive Officer, commented:

 

"Construction activities at Liqhobong were completed early in the quarter and we are currently in the commissioning and ramp up stage of the Project. We have been pleased with the tonnes processed by the plant, which has already seen nameplate production reached on multiple occasions at this early stage of ramp up.

 

As previously guided, the commencement of commissioning has seen the processing of historic low grade stockpiles, diluted ore and low grade ore from the main pit which at the end of December had produced 58,000 carats. Pleasingly, we have recovered over 20 special stones (larger than 10.8 carats) including a 37 carat white stone and numerous smaller yellow and fancy yellow stones, with no breakages of larger stones to date. At this stage of the ramp up, we have encountered the normal commissioning challenges and these are being addressed by our team in a methodical way.

 

We look forward to providing further updates on the ramp up programme, as well as the diamond sale next month."

 

Project and Commissioning Update

 

As at 31 December 2016, construction was 100% completed at Liqhobong and first ore was treated through the plant at the end of October 2016, which was well within the revised delivery target. By the end of December 2016, 402,000 tonnes of ore (being from historic low grade stockpiles, diluted ore and low grade ore from the main pit) had been treated through the plant with a total of 58,000 carats having been recovered, including over 20 special stones larger than 10.8 carats, with the largest being a 37 carat white diamond, as well as several fancy yellow diamonds.

 

As is normal during the commissioning phase of a new plant, we have had to modify or change certain operating parameters. The current grade of 14.4 carats per hundred tonnes has been below the initial commissioning estimates and the Company is currently focused on making adjustments and investigating potential causes for the under recovery of lower value finer diamonds.

 

During the commissioning process we will continue mining in the lower quality ore areas until the recoveries have reached required levels, following which we will then move into the better quality ore areas within the main pit, where the higher value diamonds are expected to be recovered. The recovery tailings from the commissioning phase are being stored separately and will be retreated once the commissioning adjustments have been made.

 

Operations at the plant have seen good volumes being treated, and on a few occasions during the ramp up stage, the plant has already met the nameplate capacity target of 500 tonnes per hour for 24 consecutive hours. The Company remains on target to achieve nameplate production by the beginning of Q2 2017.

 

During the commissioning phase we have been careful to manage costs in line with the planned tonnage volumes, at US$12 per tonne treated, we are at the bottom end of the guidance of US$12-14 per tonne.

 

The rainy season has also begun and water is being collected and stored in the various water storage facilities for future operations in the dry season.

 

Health & Safety

 

At the end of the quarter, the Project maintained its outstanding health and safety record, having reached 3.6 million man hours worked without a single Lost Time Injury.

 

Financial

 

The Company continues to manage its cash prudently. At the end of the year, cash on hand was US$4 million with US$14 million available under the ABSA debt facility and a further US$15 million available under the standby facility.

 

At the end of December 2016, 95% of the capital budget had been spent on the project with the remaining US$8 million to be spent in Q1 2017.

 

Diamond Sales

 

Firestone has scheduled its first diamond sale to take place in Antwerp in the week of 6-10 February 2017. Results are expected to be announced during the week commencing 13 February 2017. Thereafter, the Company expects to host two sales per quarter with the second auction due late Q1 2017.

 

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 ("MAR").

 

For more information contact:

 

Firestone Diamonds plc

+44 (0)20 8741 7810

Stuart Brown

Strand Hanson Limited (Nomad)

+44 (0)20 7409 3494

Stuart Faulkner

Richard Tulloch

James Dance

Macquarie Capital (Europe) Limited (Joint Broker)

+44(0)20 3037 2000

Raj Khatri

Nick Stamp

Mirabaud Securities LLP (Joint Broker)

Rory Scott

+44 (0)20 7878 3360

Ed Haig-Thomas

+44 (0)20 7878 3447

Tavistock (Public and Investor Relations)

+44 (0)20 7920 3150

Emily Fenton

+44 (0)7788 554 035

Jos Simson

Barney Hayward

 

Background information on Firestone

 

Firestone is an international diamond mining company with operations focused on Lesotho. Firestone is currently in the process of commencing production at the Liqhobong Diamond Mine in Lesotho to become a one million carat per annum producer.

 

Lesotho is emerging as one of Africa's significant new diamond producers, hosting Gem Diamonds' Letseng Mine, Firestone's Liqhobong Mine and Namakwa Diamonds' Kao Mine.

 

For more information please visit: www.firestonediamonds.com.

 

**ENDS**

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDBRGDBLGDBGRU
Date   Source Headline
13th Sep 20109:19 amRNSForm 8.5 (EPT/RI)
10th Sep 20102:32 pmPRNForm 8.3 - Firestone Diamonds plc
10th Sep 20109:00 amRNSForm 8.5 (EPT/RI)
9th Sep 20109:21 amRNSForm 8.5 (EPT/RI)
8th Sep 20108:37 amRNSForm 8.5 (EPT/RI)
7th Sep 20105:26 pmRNSSchedule 1 - Firestone Diamonds plc
7th Sep 20109:29 amRNSForm 8.5 (EPT/RI)
6th Sep 20104:15 pmRNSOffer Update
6th Sep 20108:56 amRNSForm 8.5 (EPT/RI)
3rd Sep 20104:35 pmRNSReplacement: Result of General Meeting
3rd Sep 20101:05 pmRNSResult of General Meeting
3rd Sep 20109:09 amRNSForm 8.5 (EPT/RI)
2nd Sep 20106:17 pmRNSForm 8.3 - Firestone Diamonds
2nd Sep 20107:00 amRNSTrading Statement
31st Aug 201012:01 pmRNSForm 8.3 - Firestone Diamonds Plc
27th Aug 20102:21 pmRNSForm 8.3 - Firestone Diamonds Plc
26th Aug 201012:49 pmRNSForm 8.3 - Firestone Diamonds Plc
25th Aug 201010:15 amRNSForm 8.5 (EPT/RI)
24th Aug 20109:07 amRNSForm 8.5 (EPT/RI)
20th Aug 201010:19 amRNSForm 8.5 (EPT/RI)
19th Aug 201010:26 amRNSForm 8.5 (EPT/RI)
13th Aug 20107:00 amRNSPosting of Admission Document & Updated Timetable
13th Aug 20107:00 amRNSOffer Update
4th Aug 20102:49 pmPRNForm 8.3 - Firestone Diamonds Plc
4th Aug 20102:49 pmPRNForm 8.3 - Firestone Diamonds Plc
4th Aug 201010:11 amRNSCorrected OPD Disclosure in Firestone
4th Aug 201010:10 amRNSCorrected OPD Disclosure in Kopane
2nd Aug 201010:33 amRNSForm 8.5 (EPT/RI)
30th Jul 20101:16 pmRNSOpening Position Disclosure in Firestone
30th Jul 20101:15 pmRNSOpening Position Disclosure in Kopane
26th Jul 201011:43 amRNSForm 8.3 - Firestone Diamonds Plc
26th Jul 20109:58 amRNSForm 8.5 (EPT/RI)
23rd Jul 20101:15 pmRNSForm 8.5 (EPT/RI)
23rd Jul 20109:29 amRNSForm 8.5 (EPT/RI)
22nd Jul 20102:33 pmPRNForm 8.3 - Firestone Diamonds Plc
22nd Jul 201012:44 pmRNSForm 8.3 - Firestone Diamonds Plc
22nd Jul 201012:44 pmBUSForm 8.3 - Firestone Diamonds Plc
22nd Jul 201011:46 amRNSForm 8.5 (EPT/RI)
21st Jul 201011:55 amRNSOffer for Kopane Diamond Developments plc
12th Jul 20107:00 amRNSBK11 Production Commencement
9th Jul 20101:24 pmRNSHolding(s) in Company
30th Jun 20107:00 amRNSDebswana to proceed with Jwaneng Tailings Project
30th Jun 20107:00 amRNSBK11 update
26th Apr 201011:47 amRNSHolding(s) in Company
21st Apr 201010:59 amRNSHolding(s) in Company
15th Apr 20107:00 amRNSIssue of Equity
31st Mar 20107:10 amRNSInterim Results
22nd Mar 20107:00 amRNSJwaneng Tailings Project Update
15th Mar 20107:00 amRNSSecondary listing on Botswana Stock Exchange
12th Mar 20107:00 amRNSSelected by Namdeb for new toll treatment project

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.